By using this site, you agree to the Privacy Policy
Accept
Nthanda Times
Ad imageAd image
  • Home
  • National
  • Politics
  • Health
  • Education
  • Local News
    • Parliament
    • Mining
    • Business and Finance
    • Elections
    • Technology
    • Governance
    • Human Rights
  • Environment
  • Sports
    • Airtel Top 8
    • Tnm Super League
Nthanda TimesNthanda Times
Font ResizerAa
  • Home
  • National
  • Politics
  • Health
  • Education
  • Local News
  • Environment
  • Sports
Search
  • Home
  • National
  • Politics
  • Health
  • Education
  • Local News
    • Parliament
    • Mining
    • Business and Finance
    • Elections
    • Technology
    • Governance
    • Human Rights
  • Environment
  • Sports
    • Airtel Top 8
    • Tnm Super League
Follow US
© 2025 Nthanda Times. All Rights Reserved.
- Advertisement -
Nthanda Times | National | Chitipa-Ilomba road construction progress disappoints RFA
National

Chitipa-Ilomba road construction progress disappoints RFA

Aliko Munde
Aliko Munde - Malawi News Agency
Published September 23, 2023
Share
2 Min Read

Roads Fund Administration (RFA) says it is disappointed with the slow pace on the MK34.5 billion Chitipa-Ilomba Road construction.


Chairperson for RFA, Mathews Chikankheni, said this on Thursday in Chitipa after RFA Board of Directors toured the 31-kilometre stretch, which is being constructed with funding from the government.

Chikankheni noted that half of the construction period, which is nine months, has elapsed but, on average, only six percent of work has been done.

“We are happy that we hired local contractors to do the construction works, but we are a bit disappointed with the slow pace of the construction works. We were expecting to see 50 percent of the works completed by now,” Chikankheni said.

He then asked the contractors to speed up the works this dry season, so that they catch up with the duration of the project.

“We have funding for this road project but the problem is that these contractors are slow. We release funding after the consultant certifies and issues a certificate of work done,” he said.

Chikankheni left being briefed by consultant Engineer Kaunda
Chikankheni (left) being briefed by consultant Engineer Kaunda

Roads Authority Regional Manager for the north, Engineer Charles Mtawali, was equally disappointed, saying contractors needed to beef up equipment and personnel to catch up with time.

“We only have two and half months to do the work before the rainy season starts. This is the time to utilise and catch up with the duration given.

“We are trying to develop local contractors and empower them but this is what they can give. It doesn’t augur well. They can do better,” he said.

The road is divided into three lots, with the first given to Victory Vision, Sitbec and Goka joint venture while second lot is given to Hema and Deca Construction Companies and third lot to Tahit and Chibvundiko Construction Companies.

The Chitipa-Ilomba Road,which passes through Chitipa North, takes cross-border traders to Tunduma, Tanzania.

Previous Article Lazarus Chakwera 3 DPP lawmaker Vuwa Kaunda salutes Chakwera for securing IMF trust
Next Article The suspects pose with the cannabis sativa Two get 10-year jail terms for cannabis possession
Leave a Comment

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Popular Posts

graduate

DOWNLOAD – 2025 Public university admission lists released

The National Council for Higher Education (NCHE), in collaboration with the Ministry of Higher Education, has today released the names…

By
Nthanda Times Reporter
1 Min Read
LL CITY Council visits sand mined areas in Lilongwe
Environment activist urges MEPA to call for more awareness on dangers of illegal sand Mining

Environment activists have urged Malawi Environment Protection Authority (MEPA) to create more…

3 Min Read
Chakwera 3
DPP, NAP caution government on “insensitive” borrowing as debt hits MK15.1tn

The opposition Democratic Progressive Party (DPP) and National Advocacy Platform (NAP) have…

4 Min Read
Nthanda Times
  • Quick Links
  • Live Scores
  • TNM Super League
  • Airtel Top 8
  • Privacy Policy
  • Editorial Policy
  • Cookie Policy

© 2025 Nthanda Times. All Rights Reserved.

Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?

spinner
spinner
load more